Roadworks
The works will be undertaken under a full road closure.

Work to tackle potholes begins next week

Work to reduce the number of potholes on Hull’s roads will begin next week.

Hull City Council will be laying a specialist surface treatment to 10 sections of road starting on Monday 21 October.

A total of 15, 910 sq m will be resurfaced in the areas below:

Road Section Date Traffic management
Stephenson Street Full street Monday 21 October Road closure
Griffin Road Full street Monday 21 – Tuesday 22 October Road closure
Ruswarp Grove Full street Wednesday 23 October Road closure
Arram Grove Hall Road to No 24 Wednesday 23 October Road closure
Daville Close Full street Wednesday 23 – Thursday 24 October Road closure
Wymersley Road Full street Thursday 24 – Friday 25 October Road closure
Rosedale Grove Full street Friday 25 October Road closure
Sunny Bank Brandesburton Street to Spring Grove Saturday 26 – Sunday 27 October Road closure
Dundee Street Full street Sunday 27 October Road closure
Ferensway Pearson Street junction Sunday 27 October Road closure

Councillor Harrison said: “The vast majority of these works are taking place outside of the city centre, demonstrating the council’s commitment to repairing worn road surfaces.

“We apologise in advance for any disruption caused during the period of works and ask that motorists are patient while we carry out these essential repairs.”

Advance warning signs will be in place and residents in the affected areas will be informed through letter drops.

The Guildhall. Inset, Councillor Stephen Brady.
Councillor Stephen Brady