Close-up of a roadworks sign on a pavement
(Picture: Adobe Stock)

Weekly roadworks update – 17 March

Here is the latest breakdown of roadworks taking place across Hull over the next few weeks. All works are subject to change. For the latest updates:

LocationStart dateDue dateSummary of worksUtility/HCC
A63 improvement scheme – St James Street to Market Place01/05/202001/05/2025Lane closures and local diversions until completion of scheme. LGV diversion signed via ERYC to limit number of LGVs in city centre.National Highways
A63 improvement scheme – Commercial Road26/10/202130/04/2024Enable H&S and safe systems of works for operatives working on the scheme.National Highways
Air Street06/03/202324/03/2023Gas main replacement. Road closure. Air Street closed at roundabout. Bank Side / Wincolmlee to remain open under two-way signals.Northern Gas Network
Annandale Road14/03/202317/03/2023Telecoms maintenance. junction of Falkland Road. Works to take place between 9.30am – 3.30pm. Multi-way lights will be in place during pole lift only (approx 2 hours).Three
Bellfield Avenue06/03/202313/03/2023Installation of pedestrian refuge island. Road closure between Twickenham Close and 65 Bellfield Avenue.Hull City Council
Beverley Road – Brunswick Arcade04/10/202101/04/2023Brunswick Arcade demolition. Lane closuresHull City Council
Carr Lane / Queens Dock Avenue / Dock Street / Princes Dock Steet /Posterngate / Dagger Lane17/03/202318/03/2023Road closure due to the Awakening event in Hull city centre.N/A
Cavendish Road13/02/202326/03/2023Reconstruct existing footpath. Four-way lights (manually operated 7am to 7pm). Work to be done in phases to reduce the amount of footpath closed. Footpath on opposite side to remain open during worksHull City Council
Dunvegan Road16/03/202320/03/2023Disconnect water supply. Multi-way lights. Junction of Saltshouse Road. Works to take place between 9.30am – 3.30pm. Yorkshire Water
Greenwich Ave03/04/202307/05/2023Concrete carriageway repairs. Road Closure.Hull City Council
Holwell Road29/03/202331/03/2023Telecoms maintenance. Two-way signals in place between 9.30am and 3.30pm near entrance to Co-op.O2
Humber Street 23/01/202317/04/2023Building development. Road closure outside Arco building. Closure to be in place 10am – 3pm daily.Wykeland
Kesteven Way23/01/202316/04/2023Carriageway widening and extension to zebra crossing with footpath/cycle path installations. Wawne Road closed at the approach to the roundabout with Kesteven Way. Local diversion in place.Hull City Council
Mount Pleasant/Stoneferry Road roundabout10/04/202324/04/2023Works to road surface. 20mph restriction in place and overnight closures.Hull City Council
Priory Way01/04/202231/03/2023Major improvement scheme.Hull City Council
Rosmead Street05/01/202326/05/2023Yorkshire Water drainage scheme. Full Road closure from New Bridge Road to Belmont Street. Yorkshire Water
Wincolmlee20/03/202331/03/2023Gas main replacement. Wincolmlee full closure south of Bankside roundaboutNorthern Gas Networks
Worship Street11/07/202205/07/2023Conversion of former Central Fire Station. No access to/from Freetown Way. Local diversion in place.esteem