Roadworks are to take place in Hull.
Essential repairs to Willerby Road will be carried out later this year.

Weekly roadworks update – January 14

This week it was announced that Northern Powergrid would be carrying out essential upgrades to the electricity network in Wincolmlee.

The work will begin on Monday January 31 and will last up to five weeks, during which period the road will be closed in both directions between Wilmington Bridge and Air Street.

Cllr Dean Kirk, portfolio holder for roads, highways and transport said: “Northern Powergrid has advised us that these upgrades are necessary to ensure the electricity network continues to operate reliably and safely.”

Read the full story

Below is a breakdown of roadworks taking place across Hull over the next few weeks:

Location Start Date Due Date Reason Utility/HCC Name
A63 improvement scheme – Commercial Road 26/10/21 30/4/22 Enable H&S and safe systems of works for operatives working on the scheme National Highways
A63 improvement scheme –  St James Street to Market place 1/5/20 1/5/25 Lane closures and local diversions until completion of scheme. LGV diversion signed via ERYC to limit number of LGVs in city centre. National Highways
A63 improvement scheme – Daltry Street to Rodger Milward Way 24/1/22 4/2/22 Road closed overnight from 8pm – 6am (Mon- Fri nights) National Highways
Barham Road 29/11/21 6/2/22 Carriageway resurfacing and concrete repairs. HCC – MP&I
Bellfield Avenue 10/1/22 11/4/22 Multi-way signals at the junction with Savoy Road. Manned between traffic sensitive times. HCC – MP&I
Beverley Road – Brunswick Arcade 4/10/21 1/9/22 Brunswick Arcade demolition. Contraflow in place until April 2022. Lane closure in place until Sept 2022. HCC – MP&I
Beverley Road – Mizzen Road to Windle Avenue 4/1/22 11/2/22 Construction of new cycle track and footpath on the existing footpath and verge. Lane closure. MP&I ARBPMLTD
Eglinton Avenue 21/2/22 4/3/22 Road closure due to gas mains replacement on Ings Road. Northern Gas Network
Hessle Road (12-month Scheme) 23/8/21 4/9/22 Footway reconstruction. HCC – MP&I
Holderness Road (Victor St to Southcoates) (PHASES 1-8) 4/1/22 11/9/22 Full footway reconstruction scheme. MP&I – Highways Strategy & Design
Holderness Road – Holland Street to Sherburn Street 4/1/22 13/2/22 Footway reconstruction and repaving. MP & I
Holderness Road 24/1/22 11/2/22 Excavate and locate cable, joint new cable and reinstate excavations for new connection. SWB MASS MARKET Z3
Humber Street 7/2/22 19/3/22 Installation of bollards. Works span width of footway and carriageway outside Dinostar. Work will be done in sections to maintain pedestrian walkway. HCC – MP&I
Ings Road 14/2/22 11/3/22 Works to footway and carriageway. Northern Gas Network
Leads Road 17/1/22 21/1/22 Affecting Truro Close junction, repairs to road. MS3 Networks Ltd
Lowgate Footway Repair Scheme – West Footway 22/10/21 31/1/22 Work delayed due to signal failure on A63. Northbound road closure 24/7. Work taking place 7.30am-6pm Monday to Saturday. TM taken off in conjunction with A63 closures. HCC – MP&I
Lowgate Footway Repair Scheme – East Footway 31/1/22 10/4/22 Work delayed due to signal failure on A63. Southbound road closure 24/7. Work taking place 7.30am-6pm Monday to Saturday. TM taken off in conjunction with A63 closures. HCC – MP&I
Portland Place 4/1/22 21/1/22 Essential gas repairs. Road closure, traffic to follow diversion. Northern Gas Network
Priory Way Feb-2022 Feb-2023 Major widening and construction of three signalised junctions. HCC – MP&I
Rawling Way 10/1/22 17/1/22 Resurfacing and concrete repairs. Closure between 7.30pm and 6am. HCC – MP&I
Savoy Road 14/2/22 3/3/22 Road closure due to gas mains replacement on Ings Road. Northern Gas Network
Silver Street 4/1/22 31/1/22 Road closure due to installation of automated bollards. HCC – MP&I
Stoneferry Rd Scheme – Woodhall Street to Lorraine Avenue 1/4/21 28/5/22 Major Improvement Scheme commissioned by HCC  – Infrastructure improvements and road widening. Lane closures throughout the scheme. Signals works at Woodhall street junction are now completed HCC – MP&I
Stoneferry Rd Scheme – Chamberlain Road to Bandstand roundabout 23/4/21 25/6/22 Major improvement scheme commissioned by HCC  – Infrastructure improvements and road widening. Lane closures throughout the scheme. Signals works at Woodhall street junction are now completed HCC – MP&I  COLAS
Stoneferry Rd Scheme Feb-2022 Feb-2022 Resurfacing to mainline carriageway at the Ferry Lane roundabout. Overnight road closure. HCC – MP&I  COLAS
Sutton Road 21/1/22 22/1/22 Minor, non-excavation works near Stockholm Road junction (Footway). Cherry picker to access telecoms mast for testing / maintenance works. 7.30pm – 5am.  Illuminated Stop / Go boards. O2
Wincolmlee (Phase 1) 13/12/21 17/1/22 Essential work to upgrade power supply. Multi-way signals, to be manned during traffic-sensitive times. Northern Powergrid
Wincolmlee (Phase 2) 31/1/22 4/3/22 New connection and cable upgrades. Road closure. Northern Powergrid