Roadworks sign
Road closures will be in place.

Weekly Roadworks Update – 8 October

Major restoration work to Brunswick Arcade on Beverley Road will begin next week in the interest of public safety.

From Monday 11 October, Beverley Road will be reduced to two lanes between Norfolk Street and Trafalgar Street, meaning all vehicles will share the carriageway. Traffic flow will be maintained in both directions. The work will continue until spring 2022.

Councillor Daren Hale, leader of Hull City Council, said: “This will mean a single lane in both directions and the closure of the bus lane for a small section of Beverley Road. I know as a road user of this route this is frustrating, but we cannot take any chances with public safety.”

Read more here.

A breakdown of planned works taking place across Hull has been detailed below:

 

Location Start date Completion date Details of work Organisation
A63 Castle Street – From St James Street to Market Place

 

May 2020 May 2025 Lane closures and local diversions until completion of scheme. LGV diversion signed via ERYC to limit number of LGV’s in city centre. National Highways
A63 Castle St Scheme – Closures May 2020 May 2025 Full lane closures east & west bound. Highways England
Stoneferry Rd Scheme  – Woodhall Street to Lorraine Ave 1 April 2021 28 May 2022 Installation of the Stoneferry Road corridor capital program scheme. HCC MP&I (Colas)
Stoneferry Rd Scheme
Woodhall Street to Chamberlain Road
4 October 2021 16 October 2021 Relocation of gullies. Road closure from 7pm to 6am. Hull City Council, MP&I
Stoneferry Rd Scheme – Chamberlain Road to Bandstand Roundabout 23 April 2021 25 June 2022 Installation of the Stoneferry Road Corridor scheme Hull City Council, MP&I
Stoneferry Corridor – Resurfacing full scheme 20 Sept  2021 Jan 2021 Carriageway resurfacing throughout the whole scheme Hull City Council, MP&I
Stoneferry corridor  – Woodhall Street to Chamberlain Road 18 October 21 29 October 21 Reconstruction of the carriageway Hull City Council, MP&I
Wiltshire Road (full length)

 

14 June 21 17 Oct 21 Excavate existing concrete carriageway and carry out any required concrete repairs. HCC – MP&I
Commercial Road 2 August 2021 25 October 2021 A63 Improvement scheme National Highways
Brunswick Arcade (Beverley Road) 16 August 2021 November 2022 Lane closures from October 11 Hull City Council
Lowgate 20 September 2021 8 April 2022 Paving of footpaths Hull City Council
Spring Bank West 25 October
2021
3 December 2021 Upgrading network NGN
Beverley Road LEP (Whole length – split into phases as shown below) 23 August 2021 December 2021 Create cycle lanes & junction widening Hull City Council,  MP&I
Beverley Road

(Phase 1)

23 August 2021 12 October 2021 – extended Construction of off lane cycle track. Greenwood Avenue to Hall Road Outbound. Hull City Council,  MP&I
Beverley Road

(Phase 3)

21 September 2021 13 October 2021 Construction of off line cycle track. Greenwood Avenue to City Boundary Outbound Hull City Council,  MP&I
Beverley Road

(Phase 4)

22  August 2021 17 November 2021 Construction of off line cycle track. Mizzen Road to Hall Road Inbound Hull City Council,  MP&I
Beverley Road

Inbound – Phase 1

31 August 2021 21 October 2021 Construction of Cycle Way Hull City Council,  MP&I
Beverley Road – Fountain Road 6 September 2021 22 October 2021 Implementation of cycle scheme. Work suspended during Hull Fair – white lines to be completed during w/c October 18 (one night’s work Hull City Council. MP&I
Air Street 27 September 2021 22 October 2021 Essential gas work upgrades NGN
Silver Street 4 January 2022 31 January 2022 Installing automatic bollards Hull City Council
Holderness Road
Victor Street to Southcoates – Phases 1-8
27 September 2021 September 2022 Full footway reconstruction scheme Hull City Council,  MP&I
Anlaby Road 10 October 2021 10 October 2021 Puffin crossing trial Hull City Council, MP&I
Lowgate/Market Place 14 October 2021 14 October 2021 Puffin crossing trial Hull City Council, MP&I
Caroline Street 17 October 2021 18 October 2021 Emergency – gas escape NGN
Bellfield Avenue 20 September 2021 18 October 2021 (extended) Essential repairs, footway and carriageway YW
Hawthorne Avenue 11 October 2021 15 October 2021 New connections YW
Hessle Road 14 October 2021 19 October 2021 Network Connections – lane closure YW
Saltshouse Road Delayed – awaiting new date Installation of two new pedestrian refuge islands between Dunvegan Road and Clearview Close Hull City Council. MP&I

 

 

 

Flood defences at Victoria Dock