Roadworks are to take place in Hull.
Essential repairs to Willerby Road will be carried out later this year.

Weekly roadworks update – December 3

As previously reported, Bandstand Roundabout will be closed this weekend for essential repair and resurfacing works as part of the Stoneferry improvement scheme.

The roundabout, at the junction of Stoneferry Road, Leads Road and West Carr Lane, will be closed from 7pm tonight (Friday 3 December) to 6am on Monday (6 December) to allow resurfacing work to take place.

Councillor Dean Kirk, portfolio holder for transportation, roads and highways said: “This work is a key part of the Stoneferry improvement scheme, with thousands of people using Bandstand Roundabout each day.”

Read the full story here

A breakdown of planned works taking place across Hull has been detailed below:

Location Start Date Due Date Reason Utility/HCC Name
A63 improvement scheme – Commercial Road 26/10/21 30/4/22 Enable H&S and safe systems of works for operatives working on the scheme National Highways
A63 improvement scheme –  St James Street to  Market place 1/5/20 1/5/25 Lane closures and local diversions until completion of scheme. LGV diversion signed via ERYC to limit number of LGVs in city centre. National Highways
Argyle Street 12/12/21 12/12/21 Disconnect water supply. Footpath closure with walkway in carriageway at exit from NHS car park Yorkshire Water
Barham Road 29/11/21 23/1/22 Carriageway Resurfacing and concrete repairs HCC – MP&I
Beverley Road cycle scheme 14/10/21 23/12/21 Construction of off-line cycle track. Hall Road to City Boundary outbound. Lane closure throughout duration of works. HCC – MP&I
Beverley Road – Brunswick Arcade 4/10/21 1/9/22 Brunswick Arcade demolition. Contraflow in place until April 2022. Lane closure in place until Sept 2022 HCC – MP&I
Beverley Road 8/12/21 9/12/21 Slot cutting. Beverley Road outbound between Mizzen Road and Hall Road. Lane closure 9.30am to 3.30pm StreetScene – Traffic Signals
Beverley Road 9/12/21 10/12/21 Slot cutting. Beverley Road inbound to Mizzen Road. Lane closure 9.30am to 3.30pm StreetScene – Traffic Signals
Bowlalley Lane 18/10/21 17/12/21 Footway Scheme. Extended to include carriageway. Road closure HCC – MP&I
Hall Road 10/12/21 10/12/21 Slot cutting. Multi-way lights on junction with Inglemire Lane. Works between 9.30am and noon StreetScene – Traffic Signals
Hessle Road (12-month Scheme) 23/8/21 4/9/22 Footway reconstruction HCC – MP&I
Holderness Road 6/12/21 6/12/21 Slot cutting for traffic signal loops. Signals on junction of Holderness Road and Southcoates Lane. Works to take place between 9.30am and 3.30pm StreetScene – Traffic Signals
Holderness Road  (Victor St to Southcoates) (PHASES 1-8) 27/9/21 1/11/22 Full footway reconstruction scheme. HCC – MP&I
Holderness Road 21/12/21 23/12/21 Lane closure for work to existing telecoms site in the central verge near  Summergangs Lane. T-Mobile Ltd
Holderness Road to Ganstead Roundabout 29/11/21 3/12/21 Essential  works to install communications pole. Four-way signals to be a place during pole lift from 6.30pm to 11.30pm. Carriageway will be clear at all other times. Expected to finish December 3. T – Mobile
Holwell Road 8/12/21 9/12/21 Work on existing telecoms site. Traffic Control (stop/go boards). In the footway on Holwell Road. 60m north of  Barnstaple Road roundabout. Footway closure. Alternative route will be provided. T-Mobile Ltd – Ericsson
Lowgate Footway Scheme – Lowgate 1/11/21 10/1/22 Footway repair scheme. Closed northbound from A63 to North Church Side. A63 slip road closed. Lane open southbound from Alfred Gelder Street to A63. HCC – MP&I
Lowgate Footway Scheme – Market Place 22/10/21 22/12/21 Footway repair scheme. East footway – no carriageway incursion. Except on occasions, parking bays removed to provide walkway HCC – MP&I
Saltshouse Road 1/11/21 12/1/22 Installation of two new pedestrian refuge islands between Dunvegan Road and Clear View Close HCC-MP&I
Southcoates Lane 8/12/21 17/12/21 Carriageway repair works (near Cundall Close) 9.30am to 3.30pm. Multi-way signals. Streetscene Highway Operations
Spring Bank West 25/10/21 18/12/21 Upgrading network. Opposite Albert Ave to Tile Giant (footway, carriageway) HCC – Streetscene Signals
Stoneferry Rd Scheme – Woodhall Street to Lorraine Avenue 1/4/21 28/5/22 Major Improvement Scheme commissioned by HCC  – Infrastructure improvements and road widening. Lane closures throughout the scheme. Signals works at Woodhall street junction are now completed HCC – MP&I
Stoneferry Rd Scheme – Chamberlain Road to Bandstand roundabout 23/4/21 25/6/22 Major improvement scheme commissioned by HCC  – Infrastructure improvements and road widening. Lane closures throughout the scheme. Signals works at Woodhall street junction are now completed HCC – MP&I  COLAS
Stoneferry Rd Scheme – Bandstand roundabout 26/11/21 29/11/21 Roundabout closed for road surfacing and repair work from 7pm Friday to 6am Monday. Foredyke Avenue to be two-way with restricted parking. HCC – MP&I  COLAS
Stoneferry Rd Scheme – Bandstand roundabout 3/12/21 6/12/21 Roundabout closed for road surfacing work from 7pm Friday to 6am Monday. Foredyke Avenue to be two-way with restricted parking. HCC – MP&I  COLAS
Stoneferry Rd Scheme – Chamberlain Road 6/12/21 11/12/21 Resurfacing to Chamberlain Road and roundabout.  Closure of Chamberlain Road roundabout on Stoneferry Road and along Chamberlain Road to opposite No 194. Access to/from Lorraine Street will be maintained by marshalling. Works to take place overnight. HCC – MP&I  COLAS
Stoneferry Road 13/12/21 18/12/21 Resurfacing to mainline carriageway. Closures 7pm-6pm: Stoneferry Road from exit of Glebe Road to Ferry Lane Roundabout; Ferry Lane Roundabout; Ferry Lane westbound to Ferry Lane Bridge. HCC – MP&I  COLAS
Wincolmlee (Phase 1) 13/12/21 17/1/22 Essential work to upgrade power supply. Multi-way signals, to be manned during traffic-sensitive times. All traffic management to be removed during Christmas closedown. Northern Power Grid
Trinity Market 1